Abstract
In this paper, we focus on the scheduling of preventive railway maintenance activities. The objective is to keep the railway infrastructure in good operating conditions at low costs, also taking into account the limited available resources in what concerns crew members. Equipments degrade with usage and age and a good preventive maintenance program can greatly reduce their unreliability in the sense that expectable failures can be anticipated. We propose a mixed integer programming formulation for the problem of scheduling preventive railway maintenance activities and a Variable Neighborhood Search (VNS) algorithm to solve large instances of the problem.
6 Conclusions
We address a scheduling preventive railway maintenance activities problem and propose a Mixed Integer Programming (MIP) formulation and a Variable Neighborhood Search (VNS) algorithm to solve this problem.
Computational results show that our VNS is quite efficient for the tested instances, always providing the optimal solutions for the instances where the MIP model was able to find them.