Abstract
Karaj Water Conveyance Tunnel (KWCT) is 30-km long and has been designed for transferring 16 m3 /s of water from Amir-Kabir dam to northwest of Tehran. Lot No. 1 of this long tunnel, with a length of 16 km, is under construction with a double shield TBM and currently about 8.7 km of the tunnel has been excavated/lined. This paper will offer an overview of the project, concentrating on the TBM operation and will review the results of field performance of the machine. In addition to analysis of the available data including geological and geotechnical information and machine operational parameters, actual penetration and advance rates will be compared to the estimated machine performance using prediction models, such as CSM, NTNU and QTBM. Also, results of analysis to correlate TBM performance parameters to rock mass characteristics will be discussed. This involves statistical analysis of the available data to develop new empirical methods. The preliminary results of this study revealed that the available prediction models need some corrections or modifications to produce a more accurate prediction in geological conditions of this particular project.
12 Conclusions
Based on data obtained from 8.7 km of tunnel in pyroclastic and sedimentary rocks of the Karaj formation, a comparison was made between results of the three most commonly used TBM performance prediction models and actual performance of TBM. The results indicate that the models are applicable in a special range of geological conditions and need some adjustments or correction factors to provide a more accurate estimate of machine performance in certain geological conditions